Seawater Treatment in the Port of Palermo

Customer request:

Supply the geothermal heat exchangers within the Port of Palermo directly withseawater.

The main challenge was to mitigate the typical issues associated with the marine environment, such as the presence of sand, debris, algae, and microorganisms, which—without adequate filtration—would have caused clogging, reduced thermal efficiency, and wear and tear on the system.

SATI Solution:

SATI responded with a two-stage filtration system made entirely of duplex steel to resist salt corrosion:

  • Seawater intake: An intake screen on the seabed performs an initial screening (5,000 µm), trapping large debris to protect the hydrothermal power plant.
  • Fine filtration: A series of AUTOJET automatic filters ( 200 µm) removes the finest particles and organic matter upstream of the heat exchangers.

This configuration ensures complete protection of the heat exchangers, maintaining high system performance over time and minimizing maintenance.